Microsoft data center secures backup power with RNG-fueled microgrid

RNG-fueled microgrid
Data centre. Image by Akela999 from Pixabay

Microsoft has contracted resiliency solutions provider Enchanted Rock to develop a microgrid capable of powering its data center in San Jose, California.

The microgrid would be fully supported by renewable natural gas (RNG).

In case power is lost from the utility Pacific Gas and Electric Company (PG&E), the project includes 224 0.45 MW renewable natural gas generators to provide electrical power to support the data center, according to project filings.

Have you read?
Caterpillar and District Energy St. Paul demo hydrogen-fueled CHP
Ghana mini-grid and solar PV net metering project launches

The project also includes two Tier 4 compliant diesel administrative generators with 1.25MW for one building and 0.5MW for the other.  The microgrid would include an onsite 115kV substation with two 115kV electrical supply lines that would connect to PG&E’s Los Esteros Substation.

The backup generating facility would generate up to 99MW, which is the maximum load of the data center.

Enchanted Rock plans to source RNG captured from facilities that emit methane, such as food waste and agricultural operations. Contracts are being finalised with “a major central supplier who sources from multiple sources,” according to Allan Schurr, chief commercial officer for the company.

The RNG would be injected upstream into the gas pipeline to offset the use of fossil gas.

Source: Enchanted Rock

According to Enchanted Rock, the project would out-perform current California Air Resources Board emissions requirements for distributed generation, with hourly local emissions 80%-96% lower than Tier 4 diesel standards.

“I am hopeful that one day all data centers will replace their backup power systems with carbon-negative, clean renewable natural gas,” said state senator Ben Hueso, who represents California’s 40th district. “Today’s announcement will set a precedent I believe all of California’s roughly 240 data centers should follow.”

Permits are pending for the project, which is awaiting approval from the California Energy Commission.

Enchanted Rock plans to handle monitoring, optimisation and management of the microgrid. The Houston-based developer has deployed more than 200 microgrids in the U.S., totaling 556MW of capacity.

Originally published by Kevin Clark on power-eng.com